Offing Drive

History 

A portion of Offing Drive was washed away by Hurricane Matthew on October 8, 2016. Following the disaster, the City conducted an assessment of the roadway to determine an estimated cost for repairs. The estimated cost of fix the roadway is $1 million.

Project Summary

Offing Drive remains closed at Stewart Creek. Designers are evaluating the condition of the culvert and are completing the design of the permanent repair. Upon completion of the final design, bidding and construction of the permanent repair will take place.  The permanent repair will consist of repaving the damaged portion of the roadway and will include a concrete curb and gutter and new hand rails and guardrails. 

Current Status

A utility coordination meeting was held on Friday March 24, 2017, followed by a review of the 30% design plans, structural report on the condition of the culvert and a hydrologic and hydraulic memo.  The designer is now working towards 90% design plans which should be complete by the end of this week.  This project is still on schedule for the design to be complete by 4/4/17.

Edited 3/28/2017

For questions regarding this project, please contact our Engineering Department at 910-433-1656.

Estimated Project Timeline

Project Planning

 ID Task Name  Start Date 

Estimated

Completion

Date

Projected

Duration 

Completed 
 Project Planning  10/10/2016  12/5/2016  57D  Completed
 2  Planning Meeting to discuss Emergency Access  10/10/2016  10/10/2016  1D  10/10/2016
 3 Meet with Consultants to Conduct Assessments   10/10/2016  10/10/2016 1D   10/10/2016
 4  Contact Permitting Agencies  10/19/2016  10/31/2016  13D  10/31/2016
 5  Assessments Completed  10/25/2016  10/25/2016  1D  10/25/2016

 

Project Design Team Selection Process

 ID Task Name  Start Date 

Estimated

Completion

Date

Projected

Duration 

Completed 
Project Design Team Selection Process  12/14/2016  2/27/2017  76D  Completed
 7  Draft & review team qualification requirements  12/14/2016  1/17/2017  35D  1/17/2017
 8 Advertise for Design   1/17/2017  1/17/2017 1D   1/17/2017
 9  Pre-Submittal Meeting  1/25/2017  1/25/2017  1D  1/25/2017
 10  Design Team Submittals Due  2/3/2017  2/3/2017  1D  2/3/2017
 11  Firm Selection  2/3/2017  2/17/2017  15D  2/17/2017
 12 Design Notice to Proceed  2/27/2017  2/27/2017  1D   3/6/2017

 

Design

 ID Task Name  Start Date 

Estimated

Completion

Date

Projected

Duration 

Completed 
13  Project Design by Consultant 3/6/2017  4/4/2017 30D   

 

Advertise For Construction Bid

 ID Task Name  Start Date 

Estimated

Completion

Date

Projected

Duration 

Completed 
14   Advertise for Construction Bid  3/20/2017  5/16/2017  58D
 15  Construction Contract Preparation 3/20/2017 4/14/2017  26D   
 16 Construction Contract Approval  4/17/2017  4/21/2017  5D   
 17 Advertisement For Construction Bid  4/24/2017  5/11/2017  18D   
 18 Construction Bids Due  5/11/2017  5/11/2017  1D   
 19 Construction Bid Review  5/11/2017  5/16/2017  6D   

 

Construction Contract Award

 ID Task Name  Start Date 

Estimated

Completion

Date

Projected

Duration 

Completed 
20  Construction Contract Award 5/17/2017 6/16/2017  31D   
 21 City Council Award Contract  5/17/2017  5/24/2017  8D   
 22 Contractor Acquire Bonds  5/25/2017  6/8/2017  15D   
 23 Contract Execution  6/9/2017  6/16/2017  8D   

 

Project Construction

 ID Task Name  Start Date 

Estimated

Completion

Date

Projected

Duration 

Completed 
24  Construction 6/19/2017  9/11/2017  85D   
 25 Pre-Construction Meeting  6/19/2017  6/19/2017  1D   
 26 Project Construction Bid  6/20/2017  6/20/2017  1D   
 27 Time to Complete Project Construction  6/20/2017  9/11/2017  84D