North Cool Spring Street

History 

A portion of North Cool Spring Street was washed away by flood waters from Hurricane Matthew on October 8, 2016. The upper portion of the bridge over Cross Creek was also damaged. Following the disaster, the City conducted an assessment of the roadway and bridge to determine an estimated cost for repairs. The estimated cost to repair the road and bridge is $2.4 million. 

Project Overview

The City will perform road, bridge and utility repair at the North Cool Spring Street Bridge to repair the damage caused by Hurricane Matthew.   

Project Details

  • Status:Project Complete
  • Contract / Contractor:
    • Design: STV Inc.
    • Project Management: Freese and Nichols, Inc.
    • Construction: Sandy’s Hauling and Backhoe Service, Inc.
  • Estimated Completion Date:Project is completed, road is open.

Affected Neighborhoods

  • Downtown

Contributing Departments

  • City of Fayetteville Public Services Department – Engineering Division
  • City of Fayetteville Public Works Commission (PWC)

Contacts

COF Contact: John Larch (910) 433-1656 / JLarch@ci.fay.nc.us

PWC Contact: General Inquiries (910) 483-1382 

For More Information

Current Weekly Status

The road was reopened to traffic on August 24th.

Edited 8/27/2018*

*We attempt to update page on a weekly basis. However, given the nature of the project, there may not be significant changes from week to week.

Presentation to Council on 4/10/2017.

For questions regarding this project, please contact our Engineering Department at 910-433-1656.

Estimated Project Timeline

Project Planning

 ID Task Name  Start Date 

Estimated

Completion

Date

Projected

Duration 

Completed 
 Project Planning  10/10/2016  12/5/2016  57D  Completed
 2  Planning Meeting to discuss Emergency Access  10/10/2016  10/10/2016  1D  10/10/2016
 3 Meet with Consultants to Conduct Assessments   10/10/2016  10/10/2016 1D   10/10/2016
 4  Contact Permitting Agencies  10/19/2016  10/31/2016  13D  10/31/2016
 5  Assessments Completed  10/25/2016  10/25/2016  1D  10/25/2016

 

Project Design Team Selection Process

 ID Task Name  Start Date 

Estimated

Completion

Date

Projected

Duration 

Completed 
Project Design Team Selection Process  12/14/2016  2/27/2017  76D  Completed
 7  Draft & review team qualification requirements  12/14/2016  1/17/2017  35D  1/17/2017
 8 Advertise for Design   1/17/2017  1/17/2017 1D   1/17/2017
 9  Pre-Submittal Meeting  1/25/2017  1/25/2017  1D  1/25/2017
 10  Design Team Submittals Due  2/3/2017  2/3/2017  1D  2/3/2017
 11  Firm Selection  2/3/2017  2/17/2017  15D  2/17/2017
 12 Design Notice to Proceed  2/27/2017  2/27/2017  1D   3/6/2017

 

Design

 ID Task Name  Start Date 

Estimated

Completion

Date

Projected

Duration 

Completed 
13  Project Design by Consultant 3/6/2017  4/28/2017 40D   Completed

 

Advertise For Construction Bid

 ID Task Name  Start Date 

Estimated

Completion

Date

Projected

Duration 

Completed 
14   Advertise for Construction Bid  4/14/2017  6/16/2017  45D Completed
 15  Construction Contract Preparation 4/14/2017 5/11/2017  20D   5/11/2017
 16 Construction Contract Approval  5/12/2017  5/18/2017  5D   5/18/2017
 17 Advertisement For Construction Bid  5/19/2017  6/13/2017  17D   6/21/2017*
 18 Construction Bids Due  6/13/2017  6/13/2017  0D   6/29/2017
 19 Construction Bid Review  6/14/2017  6/16/2017  3D   8/4/2017

 *Due to insufficient number of bidders, project was re-advertised causing delays.

Construction Contract Award

 ID Task Name  Start Date 

Estimated

Completion

Date

Projected

Duration 

Completed 
20  Construction Contract Award 6/19/2017 7/17/2017  20D  Completed 
 21 City Council Award Contract  6/19/2017  6/23/2017  5D   8/14/2017
 22 Contractor Acquire Bonds  6/26/2017  7/10/2017  10D  8/28/2017 
 23 Contract Execution  7/11/2017  7/17/2017  5D   

 

Project Construction

 ID Task Name  Start Date 

Estimated

Completion

Date

Projected

Duration 

Completed 
24  Construction 7/18/2017  11/20/2017  150D  Completed
 25 Pre-Construction Meeting  7/18/2017  7/18/2017  1D  8/28/2017 
26 Time to Complete Project Construction   11/6/2017  4/1/2018  150D 8/24/2018** 
           

 **Construction is now complete, however, the timeline was delayed due to change orders. The road was reopened to traffic on 8/24/2018.