The City of Fayetteville is in frequent communication with our partners at the Cumberland County Department of Public Health and health officials at local, state, and federal agencies who are monitoring the situation and providing guidance on how to respond to COVID-19. Our top priority is to maintain essential services for our community while protecting the health and safety of our residents and employees. MORE INFO

Bonnie Doone

 BONNIE DOONE @

 

Project Overview:

During a neighborhood study conducted in 2009, several projects were identified and proposed to alleviate flooding issues in the Bonnie Doone area. The investigation revealed yard, roadway, and some crawl space flooding.  The study revealed the primary contribution to flooding was the fact that none of the areas had adequate drainage systems in place.  The proposed projects consisted of implementing conveyance systems using a combination of roadside swales and pipes to provide drainage that is consistent with current City standards.  The neighborhood study identified multiple projects delineated by area.

Area 1 – This project involved installation of roadside swales along Allwood Drive and Squirrel Street and a new underground pipe network along Fieldcrest Dr.

Area 2 – The City will make improvements to the roadway gutters on Andy, Clyde, Collins, Higgins, and Cannon Streets. The City will also make improvements to the pipe systems along Andy, Clyde, and Patton Streets as well as on private property on Clyde, Collins, and Higgins Streets.

Area 5 – The City will upgrade existing drainage infrastructure and incorporate newly designed drainage infrastructure for areas without that will be capable of managing storm water flows and reduce or remove the potential for flooding.   

Area 12 – This project involved installation of roadside swales, berms, and infiltration basins along Johnson Street east of Bragg Boulevard and along Stansfield Drive.

Project Details:

Area 1 - Completed September 2017

Area 2

  • Status: Design on hold
  • Next Step: Guidance from Senior Management
  • Contract / Contractor: 
    • Design: Kimley - Horn and Associates
    • Construction: TBD
  • Estimated Completion Date: TBD

Area 5

  • Status: Design on hold
  • Next Step: Guidance from Senior Management
  • Contract / Contractor: 
    • Design: Kimley - Horn and Associates
    • Construction: TBD
  • Estimated Completion Date: TBD

Area 12 - Completed December 2017

Affected Neighborhoods:

  • Bonnie Doone

Contributing Departments:

  • Public Services Department

Contacts: 

  • City of Fayetteville Contact: Engineering Division 910-433-1656