Heat has significantly impacted the readiness of our solid waste and yard waste trucks. As a result, we haven’t had enough available trucks to maintain solid waste and yard waste pickup schedules. Equipment issues with these trucks in such hot and humid conditions as we’ve experienced over the last few weeks are not uncommon. We apologize to residents for the inconvenience. Our first priority is to pick up solid waste (green carts). Our staff is currently working on its off days of Wednesdays and Saturdays to catch up on missed routes. Our second priority is yard waste (brown carts) and it may not be collected this week. At this time, it is recommended to leave solid waste out for pickup and it will be collected as soon as possible. We hope to be back on schedule next week and will keep residents informed on our progress. 

Coventry Road Culvert and Floodplain Bench

 Coventry Coventry 2

 

Project Overview: 

The City completed culvert improvements along Buckhead Creek under Coventry Road. This project also included channel improvements along Buckhead Creek from Coventry Road to Cheltenham Road by providing additional floodplain bench on both sides and improvements to berms, therefore reducing yard and surface flooding upstream. Additionally this project included replacement and upgrades of water and sewer services.This project was a product of the Buckhead Creek Watershed Study. 

 Project Details: 

  • Status: Completed June 2018
  • Next Step: N/A
  • Contract / Contractor:
    • Design: WK Dickson
    • Construction: Wells Brothers Construction
  • Estimated Completion Date: Spring 2018

Affected Neighborhoods:

  • Sherwood Park
  • Evergreen Estates

Contributing Departments: 

  • Public Services Department
  • Public Works Commission

Contacts: 

  • City of Fayetteville Contact: Leah Harrison 910-433-1656
  • Public Works Commission General Inquiries: 910-483-1382

For More Information:

Coventry 2CoventryCOVENTRY ROAD CULVERT & FLOODPLAIN BENCH

Also a product of the Buckhead Creek Watershed Study, this project involves the addition of two culverts to the existing culvert on Coventry Road to allow for more conveyance capacity during storm flows, therefore reducing yard and surface flooding upstream. This project also incorporates a floodplain bench which will provide additional flow capacity as well as reduce erosion in the stream channel.

Construction began on this project in August 2017 and is expected to last six months.

For questions, please call me at 910-433-1656.

Coventry 2CoventryCOVENTRY ROAD CULVERT & FLOODPLAIN BENCH

Also a product of the Buckhead Creek Watershed Study, this project involves the addition of two culverts to the existing culvert on Coventry Road to allow for more conveyance capacity during storm flows, therefore reducing yard and surface flooding upstream. This project also incorporates a floodplain bench which will provide additional flow capacity as well as reduce erosion in the stream channel.

Construction began on this project in August 2017 and is expected to last six months.

For questions, please call me at 910-433-1656.