The project scope consists of repairing repetitive road settlements between the round-a-bout at Maiden Lane to Cross Creek due to aging infrastructure that is failing. This includes removing and replacing storm drain pipe, road subgrade and installing new catch basins.

Project Details:

  • Status:Design Complete, Awaiting Bid Advertisment
  • Contract / Contractor:
    • Design: WK Dickson
  • Estimated Budget: $1.1M
  • Funding: ARPA (American Rescue Plan Act) Funding
  • NTP: Fall 2022
  • Estimated Construction Time 150 Days

Affected Neighborhoods:

  • Downtown Area

Contributing Departments:

  • Public Services Department

Contacts:

COF Contact: Chris Haddock (910) 433-1656 / ChrisHaddock@FayettevilleNC.gov

Current Update as of 8/26/2022

Currently, city staff has received final bid contract and is awaiting advertising.